Material Processing

Quarry Material Handling Upgrade

Stevenson Aggregates Surge Tunnel.

MIMICO’s Engineering and Material Processing teams delivered a complete surge tunnel upgrade for Stevenson Aggregates at Poplar Lane Quarry. The project included the design, fabrication and installation of new modular surge tunnel sections, vibrating feeder units and a gravity take-up tower to improve material transfer efficiency and site reliability.
Stevenson Aggregates Surge Tunnel Project 3

Overview

MIMICO delivered a complete surge tunnel upgrade project for Stevenson Aggregates at Poplar Lane Quarry in Papamoa. The new system was designed to improve material transfer efficiency and support reliable aggregate handling throughout the quarry operation.

The surge tunnels receive aggregate product directly from a stacking conveyor before vibrating feeder units transfer material onto the tunnel discharge conveyor for processing.

Project Scope

The project included approximately 50 metres of fabricated surge tunnel sections and manufactured by MIMICO’s Auckland Engineering team.

The modular system included multiple tunnel and feeder sections to suit the site layout and material handling requirements while allowing efficient transport and installation.

Installation Works

The project involved the removal of the existing surge tunnels and conveyor infrastructure before installation of the new system.

Key works completed included:

  • Removal of existing surge tunnels and conveyor system
  • Installation of new fabricated surge tunnel sections
  • Manufacture and installation of a new conveyor gravity take-up tower
  • Reinstallation of the existing tunnel discharge conveyor onto the new gravity tower

Installation was completed by MIMICO’s Material Processing Service and Engineering teams.

Outcome

The completed upgrade provides Stevenson Aggregates with a modernised material handling system designed to improve operational reliability, maintain consistent material flow and support ongoing quarry production demands.

The modular tunnel design also improved installation efficiency and integration with the existing plant infrastructure.

Project gallery.

Project at a glance.

Customer
Stevenson Aggregates
Site
Poplar Lane Quarry, Papamoa
Scope
Surge tunnel upgrade
Tunnel length
Approx. 50 metres
Also included
Gravity take-up tower
Delivered by
MIMICO Engineering and Service

Talk to us about a similar build.

Tell us about the work your truck needs to do and our Cranes and Transport team will be in touch.

Equipment supporting this project.

Stay in the loop.

Sign-up to our monthly MIMICO newsletter. 

No spam, we promise… because your inbox deserves better.  

Name(Required)
Privacy(Required)